The first commercial windfarm was established in India by installing 1989 - Installed 250kW wind turbine generators in Gujarat. Also during the year completed 10 MW DANIDA Project in Tamilnadu. 1994 - Completed the single largest wind farm project in the country – 15MW project for Tamilnadu Newsprint & Paper Limited. 1995 - The first Indian company to obtain the ISO – 9002 Certification in Wind Turbine manufacturing. 1997 - The First Indian Company to achieve above 95% indigenisation. 1998 - Largest installation base in the country – NEPC accounting for about 30% of the total installation in the country. 2001 - Record achievement of commissioning 10.125 MW in one day. 2002 - 225/40 KW WTG certified by C-WET |
||